|
By GARY R. BROWN,
P.E.
RT ENVIRONMENTAL SERVICES
215 W CHURCH RD
KING OF PRUSSIA, PA 19406
800-725-0593
Introduction
Bioremediation has been successfully used on two South Jersey
projects, one involving a petroleum products terminal, and
another involving concrete products manufacturing facility.
In addition to significant cost savings, use of bioremediation
allowed for fast response, which was a critical element on
both projects. Both projects were implemented by RT
Environmental Services, a King of Prussia, PA environmental
services firm.
Atlas Building
Systems
Atlas
Building Systems was a former concrete products manufacturing
facility, in Voorhees, New Jersey. As required by the New
Jersey Department of Environmental Protection, the facility
was in the process of upgrading its stormwater management
system, to include the construction of two large stormwater
basins, in the rear of the facility. The facility
manufactured large scale concrete components, including such
items as bridge beams, large wall sections, and prefabricated
floor slabs. Due to the large size of the manufactured items,
the facility had a large yard area, which could not be
vegetated, and needed to remain with a sand surface, so that
the manufactured items could be allowed to cure, and shipped
in the future.
Due to
business considerations, the company announced a significant
scaling back of operations, which would result in job loss for
most of the employees at the facility. The next day, a valve
was found to be open on an oil tank, in the manufacturing
area, and several thousands of gallons of oil traveled through
the storm drainage system, and was present a product layer in
the lagoons. The release was immediately reported, and Clean
Harbors, Inc., was retained to begin product recovery
operations.
Because it was obvious that impacted soil was present around
the edge of the surface impoundments and near the inlet pipe
discharge area, bioremediation options began to be evaluated.
In addition, even though the free product was being removed
from the surface of the stormwater in the basins, there was
concern that dissolved constituents could exceed applicable
discharge limits. Stormwater discharge, once it leaves the
facility, travels only several hundreds of feet through
ditches and swales, and then flows into the Sturbridge Lakes
system, considered to be a sensitive area with recreational
uses.
As
soon as free product removal was substantially complete,
samples were obtained, which showed elevated concentrations of
several number two fuel oil parameters, well in excess of
applicable discharge limits. Concentrations of petroleum
hydrocarbons were as high as 20-40 mg/l, in excess of maximum
discharge concentrations of 1 mg/l. Further, the size and the
scale of the facility meant that it was imperative to proceed
with remediation prior to the next rainfall event, as the
volumes of stormwater produced at the facility and managed in
the lagoons, would be too large to pump or berm.
The
New Jersey Department of Environmental Protection case manager
was contacted, and a representative of the Camden County
Health Department was assigned to work with RT, due to the
time sensitive nature of the project. Two tasks were deemed
to be of critical importance:
-
Excavate the impacted soils present in a “ring” around the
edge of each basin, and, as well as the impacted soil areas
below the inlet discharge pipe.
-
Once that work was successfully completed, bioremediate by
direct mixing of cultures and nutrients, the remaining
impacted stormwater in the basins.
As excavation and field test kit
equipment was mobilized to the site, technical review of the
proposed bioremediation approach began. It was decided that
the most time sensitive approach would be to place the
impacted soils on a tarp, and cover them, as bioremediation
would need to occur using a landfarming technique, over a
several week period. Twenty to thirty cubic yards of impacted
soil were excavated.
Direct mixing of cultures and
nutrients into the stormwater then commenced. Due to the size
of the basins, there was concern that mixing would not occur,
so both pumps, and a small boat were used, to assure adequate
distribution of the bioremediation agents, over an hour or
two. As rain was forecasted to occur, at this point, as soon
as the next day, it was critical to confirm via a certified
laboratory, that concentrations had fallen to below applicable
discharge criteria. Although the field test kits were
extremely helpful in determining the extent of soils to be
remediated, and demonstrating the effectiveness of the
treatment as it occurred, only certified laboratory tests are
official. A lab within ten miles of the project site agreed
to accept samples late in the day, and run them into evening
hours, and all applicable discharge criteria meet.
Although there had been
significant concentrations of several BTEX constituents in
stormwater, all such constituents were now non-detect, and the
TPH concentration was less than the 1 mg/l discharge criteria
in the stormwater in both surface impoundments. With
immediate time sensitive goals meet, everyone breathed a sigh
relief that the approximately 225,000 gallons of impacted
stormwater was successfully treated on site, prior to the next
rainfall event, when discharge of impacted stormwater would
have been virtually unavoidable.
The following week, attention
turned to the remediation of the impacted soils. Following
approval the New Jersey Department of Environmental Protection
case manager, a landfarming area on plastic was setup, and
bioremediation agents were thoroughly mixed with soils, in a
designated area. Successful treatment of the impacted soils,
to New Jersey Department of Environmental Protection Soil
Remediation Criteria was completed within three weeks.
Compared to conventional
approaches, either involving temporary activated carbon
treatment of the stormwater, or, conventional excavation
removal and backfill of impacted soils, use of the
bioremediation approach for both had estimated projects
savings of $24,000. RT, in discussing options with plant
management, had recommended bioremediation, by explaining to
the concrete products company that the technology was first
understood and documented as a natural process, during cleanup
of the Prudhoe Bay Alaskan oil spill. The process could now
be stimulated, and would be perfect for a project such as
this.
Although management was initially
skeptical, when the bioremediation vendor was willing to offer
a guarantee of no payment unless applicable criteria were
achieved, the decision was easy. William Holub, General
Manager of the facility commented:
Mr.
Holub has traveled worldwide, and has a wealth of technical
managerial experience in cement/concrete products operations.
RT’s demonstration to him that the technology was sound and
cost effective, and satisfying DEP is a testament as to why
bioremediation should receive early consideration on all
similar petroleum release projects.
Woodruff Energy
The
New Jersey Department of Environmental Protection has a
pro-active program involving non-point source controls, which,
in the case of large petroleum facilities, requires secondary
containment around large tanks, to make the containment area
impervious. Woodruff Energy approached RT Environmental,
about the best option for upgrading of its secondary
containment area, at its facility, in Bridgeton, NJ. The
site, immediately adjacent to the Cohansey River, is a
petroleum distribution facility going back to the very
earliest parts of the 20th century. Woodruff Oil
purchased the terminal from a major oil company, in 1959. 1.6
million gallons of aboveground petroleum storage capacity is
present at the site.
Unexpected findings during the tank secondary containment
upgrading project caused the need for emergency reporting to
the New Jersey Department of Environmental Protection, when a
long abandoned buried municipal waste water treatment plant
was found beneath a former product transfer pumping station
being demolished as part of the project. Following the
initial finding of floating oil product in old treatment pits,
and because of concern that the waste water treatment system
was still connected to the Cohansey River caused a temporary
shut-down in the secondary containment upgrading project.
Upon
finding that the buried wastewater treatment plant, immediate
contacts were made with the City of Bridgeton as well as the
Cumberland County Utilities Authority. It was identified that
a municipal sewage treatment system has operated on the site
from 1883 until 1927, and investigation work began immediately
to determine the size and extent of the buried wastewater
treatment tanks at the site. DEP expressed concern that
product, or dissolved product, might be migrating to the
River, through unknown pipes or, the former wastewater
discharge system. Drawings showed a long discharge pipe to
the middle of the river.
County
utility officials were instrumental in completing an immediate
record search an RT worked closely with Lynne Mitchell of the
New Jersey Department of Environmental Protection Southern
Field Office, as well as Tim Maguire, senior DEP hydrogelogist
We began to conduct an immediate multi-phase investigation to:
-
Use data logging techniques to determine whether or not the
wastewater vaults were hydraulically connected to the
aquifer, or river which is tidal, and verify groundwater
flow directions.
-
Expeditiously determine the extent of impacted soils at the
facility, as some areas of product saturated soils were
found in the vicinity of the wastewater vaults, and some
floating product was found in the vicinity of the oil
pumping station.
-
Large
test trenches were also excavated horizontally parallel to
the river to determine and confirm that no pipelines existed
which could convey product impacted groundwater to the
River.
-
Influent
and effluent pipes to and from the wastewater treatment
vaults, as well as other pipes, including product and old,
small diameter terra cotta pipes encountered during the
excavation were all drained and properly grouted, so that
there is no potential for further migration to the nearby
River.
The
New Jersey DEP considers the Cohansey River to be in need of
environmental protection, because of presence of shell fish
beds, in the lower part of the River, in the Delaware estuary.
The
entire project was conducted expeditiously, using a team
approach. RT and DEP shared investigation approaches and
findings on a daily basis, following a DEP visit to the site
by senior officials from the Southern Field Office. With
winter approaching, and the lining project shut down the key
concerns were:
-
Completing the investigation project such that secondary
containment lining could still be installed before cold
weather arrived (HDPE selected for secondary containment
cannot be installed in low temperature conditions).
-
As
the previous secondary containment earthen berms had to be
opened for the entire project, all parties felt it important
to proceed with the work expeditiously, so that the
secondary containment could be put back in place.
-
All
expressed a desire to work closely together using a high
degree of careful technical focus to reach common
understandings on the specific goals and need for each
investigation and remedial step, and to work quickly towards
a solution.
The Project turned into a model of
cooperation meeting with full intent and spirit of the New
Jersey ISRA/Brownfields law. Although many people are under
the impression that the Brownfields Law only applies to
contaminated, abandoned urban sites. ISRA revisions also in
the law actually allow DEP to adopt flexible and appropriate
standards, for petroleum release sites using a risk based
corrective action process. RT worked closely together with
DEP to use appropriate standards as localized areas around the
waste water treatments vaults were investigated, taking into
account that the area would be capped by the secondary
containment liner. Also taken into the account were the
investigation results, the site setting, and migration
potential.
Once it was demonstrated that all
potential migration pathways of concern to the river had been
located and successfully closed, Class II soil standards were
found to be applicable and remedial needs were focused on two
particular “hot spot areas”, which were expeditiously
remediated by excavation and removal of soil. Soil was
shipped to a regional bioremediation facility for treatment.
Engineering and investigation findings, as well as lab
results, and key technical findings were forwarded to DEP by
fax on a daily basis and investigation and remediation of the
entire tank farm/wastewater treatment area was completed in a
short three weeks.
At the availability of a local
bioremediation option was very important to the overall
project, from both a cost and schedule standpoint. The
project involving the secondary containment installation only
suffered minimal delay, because of the availability of the
local bioremediation option. Trucks that were used to haul
the petroleum impacted soils from the site were used to haul
already clean bioremediated soils back to the site,
eliminating double handling, maximizing remedial project
productivity.
The extra remedial portion of the
project, to include the free product removal, and
excavations/removal/replacement of the petroleum impacted
soils had a total cost of $54,000. Savings on the project,
attributed to the DEP’s use of flexible standards, as well as
the use of bioremediation, totaled approximately $37,000,
arrived at by comparing with the next most cost effective
option.
Mr. Robert Woodruff, Sr.,
President of Woodruff Energy, commented that:
“the level of cooperation was
remarkable, in that daily investigation and remediation work
could be planned and implemented with DEP oversight so as to
be both focused and efficient. We thought that the costs
for dealing with the treatment plant problem could have been
much higher.”
In
all, more than 300 tons of soil were bioremediated, The
project was a model of cooperation and provides the assurance
that Woodruff’s main tank farm facility has been through the
investigation and remediation process so that areas under the
liner system, are no longer of environmental concern.
Woodruff Energy is one of New Jersey’s ISRA/ Brownfields
success stories, wherein fresh technical approaces including
bioremediation and a high level of cooperation prove that
environmental work can proceed quickly, efficiently, and
professionally
Conclusion
RT
Environmental Services has been implementing bioremediation,
on a wide variety of projects, since 1993. Although
bioremediation is not applicable to every type of potential
petroleum release project, where it is technically appropriate
and can be applied, the advantages can bring to a project are
substantial. These include:
-
Minimizing waste.
-
Being able to respond to a release quickly, where surface
water is involved.
-
Having the opportunity for cost savings.
-
Minimize project delays.
-
Avoiding backfill costs.
Due to
these attributes, RT recommends bioremediation receive first
consideration, when deciding how to deal with petroleum
releases. Knowing how and when to implement the technology
can lead to a high degree of project success, even when there
is a big bump in the road.
Top |