|
Randy Hiebert1, Robert Sharp2,
Al Cunningham3, and Garth James
1
1 – MSE
Technology Applications, Inc., Butte, MT, USA
2 – Environmental Engineering Department, Manhattan College,
Riverdale, NY, USA
3 – Center for Biofilm Engineering, Montana State University,
Bozeman, MT, USA
A novel
technology for the containment of contaminated groundwater has
been developed using bacterial biofilms to “plug” aquifer
material, producing a subsurface biofilm barrier.
Installation of a biofilm barrier consists of injection of
starved bacteria downstream from the contaminant plume via a
series of injection wells. The starved bacteria are
environmental isolates selected from the contaminated site for
their ability to produce copious amounts of biofilm. These
cells are mass-produced and then starved to reduce their size
and enhance their subsurface transport properties. The
starved bacteria are introduced to the aquifer with injection
water where they migrate through the porous media and adsorb
along the flow paths. A selective nutrient feed is injected
into the aquifer following cell inoculation. When the
nutrient feed reaches the starved bacteria, they are
“resuscitated” and begin to grow, attach, and produce a
biofilm within the aquifer material. As the biofilm develops,
it fills the pores of the aquifer material, reducing the
hydraulic conductivity of the aquifer by as much as 99.99%,
attenuating the transport of contaminants further down stream.
A great
deal of laboratory and pilot-scale research has been performed
to thoroughly understand and develop the starved cell
subsurface biological barrier to a point where it can be
applied effectively in the field. This research included:
characterizing the transport and resuscitation properties of
starved cells in porous media; understanding the benefits and
limitations of using starved cells to produce sub-surface
biofilm barriers; and developing a protocol for designing,
installing and maintaining site-specific biofilm barriers.
The culmination of this research has been a full-scale
demonstration of the starved cell biofilm barrier by MSE
Technology Applications, Inc. (MSE) in Butte, Montana. The
test cell is a fully contained and hydraulically controlled
man-made aquifer that is 180 feet long, 130 feet wide and 20
feet deep. Prior to barrier formation, the effective ground
water velocity through the site was established at
approximately 1.0 foot/second. The demonstration site was
homogeneous and had an initial hydraulic conductivity of
approximately 0.02 cm/sec., with a constant applied head of
0.002 ft/ft. The highly permeable soil, low groundwater
temperature, and relatively large applied hydraulic head
represented a difficult plugging scenario. In other words, if
an effective barrier could be formed under these “worst-case”
conditions, the average subsurface situation should be
relatively easy to plug.
In
preparation for barrier formation, the bacterial cells were
grown in large quantities and starved for 4-6 weeks using a
highly effective, proprietary starvation procedure developed
by MSE. The biofilm barrier was installed by injecting
concentrated starved cells and a low cost, high carbon,
nutrient rich growth substrate into the aquifer using a series
of injection wells. Flow of fresh groundwater was maintained
while the bacteria and nutrient solutions were being applied.
Hydraulic conductivity was monitored via a series of
monitoring wells up-stream and down-stream of the barrier
wall. The installation and development of the biofilm barrier
wall was achieved using a series of injection and recovery
wells to concentrate the cell mass, and the subsequent biofilm
growth, through the middle of the site. The well-spacing and
pumping rates used to achieve a relatively thin and continuous
wall across the site were determined using hydrogeologic
modeling software. This also helped reduce the loss of the
starved cell inoculum and nutrient feed due to the high flow
rates through the system, thus reducing costs and installation
time.
The initial
drop in hydraulic conductivity was rapid, but the full
permeability reduction took approximately 8 weeks due to the
high initial permeability and relatively large hydraulic
head. In addition, the groundwater temperature of about 7
degrees Celsius slowed the in-situ biofilm growth and
development at the site. However once the biofilm barrier was
established a 99.8% reduction in over-all initial hydraulic
conductivity across the site was achieved.
Due to the
high initial permeability of the site, the relatively high
flow rate, and the desire to establish a barrier quickly, the
initial feeding of the barrier required more nutrient than
initially predicted. However, once the biofilm barrier was
established it remained highly effective for many months
without the need for additional nutrient.
For the
first six months after the biofilm barrier was established no
nutrient was added and the biofilm barrier maintained an
average of 99.7% reduction in hydraulic conductivity. A small
nutrient feed was added to the south end of the wall where the
hydraulic conductivity was highest. This nutrient addition
was used as an opportunity to monitor the performance of the
biofilm barrier wall in response to maintenance feeding.
After the addition of 0.2 pore volumes of nutrient to the
system, the average hydraulic conductivity of the biofilm
barrier wall dropped an additional 45% to achieve greater than
99.8% reduction in the initial hydraulic conductivity (from
0.02 cm/sec to 0.00004 cm/sec).
The biofilm
barrier is concentrated along a relatively thin wall across
the site. The hydraulic conductivity of the biofilm barrier
increases at the ends of the wall due to side channeling and
wall effects. This diagram demonstrates the ability to
effectively and accurately place the biofilm barrier wall
in-situ. The accuracy of the biofilm barrier placement is
a function of starved cell subsurface transport
characteristics and the combination of nutrient feed loadings,
and the spacing and operation of the injection and recovery
wells during the installation and development of the biofilm
barrier wall.
The starved
cell biofilm barrier demonstration is ongoing, and is planned
to continue for at least the next 12 months. During this
time, tests will be performed on the barrier wall to determine
its long-term performance, and the need and effectiveness of
maintenance feeding. In addition, tests are currently being
conducted on the demonstration barrier wall to determine the
ability of this particular barrier to carry out in-situ
denitrification. Future plans are being made to demonstrate
the starved cell biofilm barrier technology in a number of
applications including: containment of leaky underground
storage tank plumes, redirection of groundwater plumes to
enhance the effectiveness of existing treatment processes,
construction of in-situ cut-off walls for reducing salt
water intrusion into fresh water aquifers, and the plugging of
high permeability zones in oil fields to enhance secondary oil
recovery operations.
The starved
cell biofilm barrier wall is an attractive alternative to
other barrier technologies (grout curtains, slurry walls,
sheet piling, etc.), because it does not require excavation,
it utilizes indigenous bacterial populations, it requires
minimal maintenance, it has no depth limitations, and
installation and maintenance costs are lower than other
barrier technologies. Under reasonable site conditions
(hydraulic conductivity and hydraulic head) the barrier wall
can likely be installed quickly and requires maintenance
feeding only once every 12-24 months. In addition, the
biofilm barrier wall is self-healing with the addition of a
small amount of nutrient, and can be constructed around all
type of heterogeneities (pipes, clay lenses, rock formations
etc.) and in all types of soil (high and low permeability,
fractured rock, etc.). Finally, with the use of horizontal
wells, the starved cell biofilm barrier can also be placed
under buildings and in areas where the use of large excavation
equipment may not be feasible.
Ongoing
research includes investigation of new applications of biofilm
barriers. One new type is single and multiple-species
reactive barrier walls, which simultaneously reduce plume
migration while degrading the contaminant. Reactive biofilm
barrier walls capable of denitrification, and degradation of
BTEX, chlorinated aliphatics, and PAHs are currently being
developed.
A large
portion of this work was funded by the U.S. Department of
Energy under contract number DE-AC22-96EW96405.
Top |